is there a possibility to generate a PR/PO automatically to fill up negative stock in a storage location (IM). E.g. you create negative stock to post a goods issue for a delivery. At the end of the day I want to create one PR/PO to refill the stock.
Thanks
Iris
normally the MRP-Run automatically creates purchase requisitions or planned orders to cover negative availabilities.
Then you can set up a job to automatically convert them into purchase orders or production orders.
Purchase; ME59N, Production: CO41 can be planned as jobs after the MRP run.
But therefore the material master data, routings and purchase info records need to be maintianed 100% complete.
Saute
Anwendungsbetreuer PP/PM/PDM/VC/G.I.B DC
SAP ECC 6.0 EHP8, bald S/4 Hana PC